Valley Drive Parking Lot Schedule (Weather Permitting):
Concrete Header Curb Install
- March 29-30, Concrete Header Curb install – Parking Lot closed
 - March 31 – Parking Lot open for normal parking
 
Asphalt repairs
- April 10 – 11, Mill, Pave, Stripe, and Asphalt Curb Install
 - April 12 – Parking Lot open for normal parking.
 
